Dorian Hotel

Client / Owner
EllisDon Construction
Scope of Work
Structural Foundation Walls
Contract Value
$135,000.00
Project Description
Integrity Shotcrete Inc. was awarded the shotcrete installation of the below-grade foundation walls of the Dorian Hotel, located on the corner of 5th Avenue and 5th Street SW, in Calgary, AB.

The shotcrete was placed against a temporary secant wall with a waterproofing membrane. The underground parkade was 4 levels below grade, but a small overall footprint. Due to land agreements and utilities, corner braces were required on all four corners, limiting access and increasing complexity on each shoot.

The Contractor and Owner had an aggressive completion schedule. Integrity Shotcrete worked closely with the Contractor and Owner in the pre-planning of the project to ensure the schedule would be met. As a result, we completed the shotcrete scope of work on schedule, per the originally scheduled shoots.

Over 500m3 shotcrete was shot in 11 scheduled shoots. By not tying up the site crane and providing a significant improvement on the schedule and overall project costs, the use of shotcrete for the below-grade foundation walls increased the overall efficiency of the construction of the foundation. The Client, Contractor and Consultant all recognized the benefits of shotcrete for below-grade foundations.



Project Gallery