The locations of the repairs were on the vertical walls and overhead soffits. A shotcrete solution and method was selected as there was no feasible way to conventionally form the locations while they were either active or had short shutdown windows. Integrity Shotcrete provided a proposal for the partial depth repairs that included a pre-production test panel in vertical and overhead positions. After the initial pre-production tests, the concrete mix design was modified slightly to maximize performance.
Upon approval of the mix design, shotcrete methods and performance testing, we conducted the first production shoot along the 78th Avenue Bridge. Additional in-situ testing was performed to test the shotcrete method and mix for the application and tension properties when placed against the existing concrete substrate.
All tension (pull) tests and compression tests exceeded the project requirements, and the method was approved for full production use. The work was completed in the LRT tunnel where only 48 shutdown hours were approved. Additionally, the partial depth repair work was used in the active CPR tunnel that had to be cleared of activity when daily trains passed through the work area. The use of shotcrete was determined to be extremely successful and the only reasonable method that could have been used for the soffit repairs while keeping areas active or limiting shutdowns. Both the Contractor and Consultant deemed the shotcrete method as a very effective method for future concrete partial depth repairs.